TRAINING AND MOCK
DRILL (Chapter-16) |
Trained manpower is an essential ingredient
of any DM system, Mere provision of sophisticated equipment without trained manpower
is futile. For handling on unforeseen situation like managing a Disaster,
training of all railway personnel concerned is an inevitable input. To acquire
necessary knowledge and skill, all relevant officials should be given periodic
training regarding their duties and that of their department.
16.1
TRAINING
16.1.1 Training should be conducted at the following three levels
i. Individual Training
a.
For enhancing the skill of staff attached to ARMVs, ARTs,
etc., supervisors and staff shall be given general training in Disaster
Management.
b.
Special training may be arranged in Extrication, Rescue,
Medical relief Rolling stock restoration technique and civil Defence by
departments concerned.
ii. Seminars/Workshops : Seminars should be periodically conducted
on Disaster preparedness, and the DM Plan.
iii. Joint Exercises : Full scale Disaster Management Mock Drill
to be conducted as detailed below.
16.2
FULL SCALE MOCK
DRILL
Disaster
Management essentially necessitates a state of preparedness under all
circumstances and the efficacy of arrangements therein can be assessed only by
conducting periodical full scale mock drills.
16.2.1 Objective of the full scale mock drill would be to
i. Gauge the
preparedness of DM system including detailed planning and keeping of all
equipment in good fettle.
ii. Integrate the
operational response to measure overall
performance a the exercise.
iii. Measure
performance with regard to accident restoration.
iv. On a division,
the first mock drill should be conducted within 3 months of issue of the Zonal
DM Plan.
v. On a division,
the second mock drill should be conducted 3 months after the first one, in
order to correct all shortcomings noticed during the first mock drill.
vi. Thereafter, mock
drills shall be conducted once every 2 years after the new DRM takes over.
vii. It should be
conducted during the day and in a branch line section.
viii.
6 hrs. traffic block shall be taken and the ARMV/ART run out
to the accident site.
ix. UCC and CAC
should be set up and each department will post their functionaries in the
Control Office as also in UCC and CAC.
x. All facilities
should be provided in UCC and CAC by departments concerned.
16.2.2
During these full
scale mock drill, following aspects shall be closely watched
i. Turning out of
ARMV/ART within the prescribed time.
ii. Speed of the
specials.
iii. Assembly of
staff.
iv. Handing of ART,
HRDs, HREs and other rescue equipment.
v. Logging of
events.
vi. Functioning of
field telephones and communication network.
vii. Functioning of
generator sets, lighting equipments.
viii.
Preparedness of first-aiders and availability of medical
equipment.
ix. Preparedness of
commercial department to mobilize adequate manpower.
x. On completion of
the drill, a
detailed report shall be prepared detailing deficiencies noticed, corrective
measures initiated and improvements required.
Home Page Contents Previous Page Next Page