| SALIENT FEATURES |
| Length |
98.095 Km.'s |
| Cost |
Rs.427,65 lakhs |
| State |
Orissa |
| Division |
Khurda |
| Chief Engineer |
CE/C/I/BBS |
| Progress (Physical) |
0.20% |
| Progress (Financial) |
0.16% |
|
| |
| |
This is an important project connecting Paradeep Port. to Eastern mineral rich area of Orissa.Angul-Sukinda Road new BG line will serve the power plant being set up at Duburi in Private Sector, apart from catering to the needs of the Steel Plants being set up in that area.
Progress of Works
- Final Location Survey has been completed.
- Land acquisition is in progress.
- Estimate being sent to Railway Board
|
| |
| |
|
| |
|
|
 |
|
 |
 |
 |
|
|
 |